Skip to Content

Tutor Perini lands $31M in change orders for San Francisco subway project, ConstructionDive, ft. Andrew Richards

Posted Sep 30, 2019

Andrew Richards, co-managing partner at Kaufman Dolowich & Voluck, LLP in Long Island and chair of the KD construction practice group, was quoted in an article on change orders and construction projects written by Kim Slowey for Construction DIVE (September 26, 2019) –

Dive Brief:

  • In a filing with the U.S. Securities and Exchange Commission, general contractor Tutor Perini revealed Tuesday that it has received a contract change order in the amount of $31.2 million as compensation for delays on the San Francisco Municipal Transportation Agency’s (SFMTA) $1.6 billion Central Subway project.
  • Tutor Perini indicated that the delays were a result of unforeseen site conditions and changes in the project design. The SFMTA has already paid $29.7 million toward the change order, which represents payment in full minus an agreed-upon retainage of $1.5 million. 
  • Tutor Perini said it will continue to pursue additional, unresolved change orders on the Central Subway project and expects those negotiations to wrap up as early as the end of this year.

One of the big disagreements between Tutor Perini and the SFMTA had to do with the type of track one of the project’s subcontractors installed. The SFMTA argued that the project required high-strength steel track rather than standard-strength track provided and wanted Tutor Perini and its subcontractor to replace it at their own expense, a change estimated at $2.6 million. The San Francisco Examiner later reported that the SFMTA might have known that the standard-strength steel was being used. 

Generally speaking, even when relationships are friendly between public agencies and contractors, said Andrew Richards, attorney and chair of the construction practice group at Kaufman Dolowich & Voluck, LLP in New York City, it can be very difficult to negotiate change orders, particularly in New York. One of the main issues is that many agencies simply don’t want to pay amounts beyond what is in the original contract. “It’s easier for them not to pay than go over budget,” Richards said.

And if the relationship is contentious, he said, many agencies will use contract terms, such as contract notice provisions, to deny claims. “There are many types of those clauses in a public agency contract in New York, and they use them as a hammer,” he said. It’s horrible.”

Richards’ advice to those contractors who might have reason to submit a change order to a public agency is to comply with all of the notice provisions and conditions precedent in the contract. If not, he said, then the agency could move to dismiss those claims. “It happens every day,” Richards said. ​

Read more at the full article.

Awards & Honors

No aspect of the advertisement has been approved by the Supreme Court. Learn more about the selection methodology of awards and honors.

Mansfield Rule Certified 2023 Super Lawyers Super Lawyers Best Law Firms 2025 Martindale Hubbel AV Preeminent Law 360